EXTENSION OF TIME TO LODGE AN APPEAL TO PPAA UNDER PP RULES, 2005
3 posters
Page 1 of 1
Re: EXTENSION OF TIME TO LODGE AN APPEAL TO PPAA UNDER PP RULES, 2005
Dear freddy,
More explanation is needed justifying your request for extension of time for appeal. Pursuant PPA 2011 clause 107(2), every order, direction or appointment which was issued, given or made pursuant to the provisions of PPa 2004 shall remain valid.
This is the room for appeal under the new legislation but justification is important.
More explanation is needed justifying your request for extension of time for appeal. Pursuant PPA 2011 clause 107(2), every order, direction or appointment which was issued, given or made pursuant to the provisions of PPa 2004 shall remain valid.
This is the room for appeal under the new legislation but justification is important.
GWK- Posts : 55
Join date : 2014-03-24
Age : 56
Location : DAR ES SALAAM
EXTENSION OF TIME TO LODGE AN APPEAL TO PPAA UNDER PP RULES, 2005
Dear Mpangala,
The referred Regulations are no longer valid. You can obtain details from Regulations 2013 of GN. No.446
The referred Regulations are no longer valid. You can obtain details from Regulations 2013 of GN. No.446
freddy.mbeyella- Posts : 74
Join date : 2009-08-25
EXTENSION OF TIME TO LODGE AN APPEAL TO PPAA UNDER PP RULES, 2005
Hello dear forum members,
Please, let me know if the Public Procurement Appeal Rules, 2005, stipulates for extension of time to lodge an appeal to the Authority and, if the Rules provide nil, what is the practice for lodging appeal to PPAA out of time?
Mpangala
Please, let me know if the Public Procurement Appeal Rules, 2005, stipulates for extension of time to lodge an appeal to the Authority and, if the Rules provide nil, what is the practice for lodging appeal to PPAA out of time?
Mpangala
Mpangala- Posts : 1
Join date : 2014-03-07
Similar topics
» Appeal to PPAA against Blacklisting under PPA 2011
» PPAA RULINGS
» lead time management in Public organization
» PPAA Review the PPRA’s Decision Arising from Blacklisting of Tenderers – PPA 2011
» Appeal Case No. 32 of 2015-16 M/s Brothers Contractors vs Mzumbe University - BANK STATEMENT
» PPAA RULINGS
» lead time management in Public organization
» PPAA Review the PPRA’s Decision Arising from Blacklisting of Tenderers – PPA 2011
» Appeal Case No. 32 of 2015-16 M/s Brothers Contractors vs Mzumbe University - BANK STATEMENT
Page 1 of 1
Permissions in this forum:
You cannot reply to topics in this forum
|
|
Wed Dec 18, 2019 9:13 pm by yohanaamon@yahoo.com
» Is non-submission of invalid CRB receipt voucher a major deviation?
Tue Dec 17, 2019 1:00 am by RJM
» MAKANDARASI KUWEKWA NDANI KWA KUTOKAMILISHA MIRADI NDANI YA MUDA
Tue Dec 17, 2019 12:46 am by RJM
» How Supplier can register in e-Procurement system (TANePS)
Thu Dec 12, 2019 5:48 am by pms
» Kukosekana risiti ya ununuzi wa tenda
Sat Apr 27, 2019 6:05 pm by ALLY MUNIR
» IS IT TIME TO THINK OF DEACTIVATING TENDER BOARDS AND INTRODUCE A MECHANISM OF PROCUREMENT PROFESSIONAL OPINION?
Thu Apr 11, 2019 3:40 pm by pms
» e-Procurement System is now operational
Thu Apr 11, 2019 3:14 pm by Admin
» TENDA ZINAPOKOSA WAOMBAJI
Thu Jan 10, 2019 10:42 pm by thanksme
» Attendance of District Treasurer in Council Tender Board meetings
Mon Mar 19, 2018 8:57 pm by GWK