CHANGE IN THE QUANTITIES EmptyWed Dec 18, 2019 9:13 pm by yohanaamon@yahoo.com

» Is non-submission of invalid CRB receipt voucher a major deviation?
CHANGE IN THE QUANTITIES EmptyTue Dec 17, 2019 1:00 am by RJM

» MAKANDARASI KUWEKWA NDANI KWA KUTOKAMILISHA MIRADI NDANI YA MUDA
CHANGE IN THE QUANTITIES EmptyTue Dec 17, 2019 12:46 am by RJM

» How Supplier can register in e-Procurement system (TANePS)
CHANGE IN THE QUANTITIES EmptyThu Dec 12, 2019 5:48 am by pms

» Kukosekana risiti ya ununuzi wa tenda
CHANGE IN THE QUANTITIES EmptySat Apr 27, 2019 6:05 pm by ALLY MUNIR

» IS IT TIME TO THINK OF DEACTIVATING TENDER BOARDS AND INTRODUCE A MECHANISM OF PROCUREMENT PROFESSIONAL OPINION?
CHANGE IN THE QUANTITIES EmptyThu Apr 11, 2019 3:40 pm by pms

» e-Procurement System is now operational
CHANGE IN THE QUANTITIES EmptyThu Apr 11, 2019 3:14 pm by Admin

» TENDA ZINAPOKOSA WAOMBAJI
CHANGE IN THE QUANTITIES EmptyThu Jan 10, 2019 10:42 pm by thanksme

» Attendance of District Treasurer in Council Tender Board meetings
CHANGE IN THE QUANTITIES EmptyMon Mar 19, 2018 8:57 pm by GWK

May 2024
MonTueWedThuFriSatSun
  12345
6789101112
13141516171819
20212223242526
2728293031  

Calendar Calendar

Statistics
We have 1676 registered users
The newest registered user is esagile

Our users have posted a total of 1240 messages in 351 subjects
Who is online?
In total there are 3 users online :: 0 Registered, 0 Hidden and 3 Guests :: 1 Bot

None

[ View the whole list ]


Most users ever online was 225 on Sun Oct 03, 2021 4:24 pm

CHANGE IN THE QUANTITIES

3 posters

Go down

CHANGE IN THE QUANTITIES Empty Re: CHANGE IN THE QUANTITIES

Post  Akida Sun Sep 05, 2010 12:41 am

the percentage 15 or 1 have been used to control scope. if the changes are more than 15% it is assumed that even the methodology of executing the work might be different. eg. the equipments used or type of working tools might also change and thus the price.


Akida

Posts : 6
Join date : 2010-07-28

Back to top Go down

CHANGE IN THE QUANTITIES Empty Re: CHANGE IN THE QUANTITIES

Post  RJM Thu Aug 27, 2009 10:23 pm

GadielCM, by virtue of the Regulations you have cited, I think it is high time now we harmonize the referred Clause 41 with these Regulations. Or practically, how the current situation should can be handled?
RJM
RJM

Posts : 260
Join date : 2009-07-30
Age : 73
Location : What is written without effort is in general read without pleasure

Back to top Go down

CHANGE IN THE QUANTITIES Empty CHANGE IN THE QUANTITIES

Post  GadielCM Wed Aug 26, 2009 7:27 pm

RJMbishi!, any alteration and amendment (R43) any variations (R44), any additional works, and any Amendments after signature (R117-2,3,4,5)/GN97 allowed for the benefit and advatagious for PE/Government and so, the PM allowed to do any one of the mentioned above with the approval by appropriate tender board only.

GadielCM

Posts : 69
Join date : 2009-08-21

Back to top Go down

CHANGE IN THE QUANTITIES Empty CHANGE IN THE QUANTITIES

Post  RJM Tue Aug 04, 2009 5:26 pm

Can someone help to interpret correctly Clause [Changes in the Quantities] which can be found in both Standard Bidding Documents for Smaller Works and Medium & Large Contracts in relation with the Section of 69 (2) [Alteration and Amendments] of the PPA, Cap 410, Section 30 (b) [Functions of Tender Board] of the PPA, Cap 410 and Regulation 177 [Amendments after Signature] of GN No. 97 of 2005. In short all these provisions require any amendment of the original contract to be made after approval of the Tender Board.


See referred Clause extracted from the Standard Bidding Document.

41. Changes in the Quantities 41.1 If the final quantity of the work done differs from the quantity in the Bill of Quantities for the particular item by more than 25 percent, provided the change exceeds 1 percent of the Initial Contract Price, the Project Manager shall adjust the rate to allow for the change. [I believe the end result of adjusting the rate to allow for that change will constitute variation of the original contract whether reduction or addition of the original sum. Does Project Manager need to get approval of the Employer provided that the change does not exceed 1% of the original contract price?]
41.2 The Project Manager shall not adjust rates from changes in quantities if thereby the Initial Contract Price is exceeded by more than 15 percent, except with the prior approval of the Employer. [Does the Project Manager allowed to adjust rates from changes provided that the change exceeds 1% and is equal or below 15% of the initial contract price without approval of the Employer?]
41.3 If requested by the Project Manager, the Contractor shall provide the Project Manager with a detailed cost breakdown of any rate in the Bill of Quantities.
RJM
RJM

Posts : 260
Join date : 2009-07-30
Age : 73
Location : What is written without effort is in general read without pleasure

Back to top Go down

CHANGE IN THE QUANTITIES Empty Re: CHANGE IN THE QUANTITIES