Latest topics
Statistics
We have 1676 registered usersThe newest registered user is esagile
Our users have posted a total of 1240 messages in 351 subjects
Who is online?
In total there are 6 users online :: 0 Registered, 0 Hidden and 6 Guests None
Most users ever online was 225 on Sun Oct 03, 2021 4:24 pm
commecement contract.
2 posters
Page 1 of 1
Re: commecement contract.
Ramadhan, generally the Contract Commencement Date sometimes referred as Contract Effective Date depends very much on the Form of Contract you are using and the wording of the terms and conditions governing the contract.
Normally the contract should have a date stated as the Contract Date/Contract Effective Date or Contract Commencement Date. This date is not necessarily the date when the contract was signed or letter of acceptance was issued but rather the date from which all the contractual rights and obligations begin and from which point any term of time, usually commences. In other words, date when the parties to the contract starting to perform their obligations in the contract.
I will try to breakdown your concerns based on the PPA 2004 and its Regulations and Form of Contract issued by PPRA as well as practice in other Form of Contracts.
According to S55(7)/PPA2005 “the procurement contract shall enter into force when a written acceptance of a tender has been communicated to the successful supplier, contractor or consultant”. To me this doesn’t mark the Contract Commencement Date but rather establishing the contract between the parties [offer + acceptance = contract]. For the parties to the contract to start performing their obligations there are conditions precedent must be meet in order to fix the Contract Commencement Date. One of these conditions is the submission of the Performance Security and signing of the contract within 30 days after receipt of the Letter of Acceptance.
Site Possession Date is the date when the contractor is given full access to the site by the client for temporary and permanent works. Logically, this cannot happen before the conditions precedent mentioned above are fulfilled by the contractor as ITB Clause [Performance Security] warrant the client to cancel the award and take any remedy under contract and resort to awarding the contract to the next ranked tenderer in case successful tenderer failure to comply with conditions precedent.
According to Clause 18 [Commencement and Completion] of the Form of Contract [Smaller Works Contracts] issued by PPRA, “The contractor may commence execution of the on the Start Date [stated in SCC] and shall carry out the works in accordance with programme submitted by the contractor, as updated with the approval of the Project Manager, and complete them by the Intended Completion Date [stated in SCC]”. The same Form of Contract Clause 24 [Possession of the Site] states that “The employer shall give possession of the site to the contract. If the possession of a part is not given by the date stated in the SCC, the employer will be deemed to have delayed the start of relevant activities, and this will be a Compensation Event”.
FIDIC – Form of Contract
In the 1999 FIDIC Conditions of Contract, Sub-Clause 8.1 [Commencement Date] states that "The Engineer shall give the contractor not less than 7 days’ notice of the Commencement Date. Unless otherwise stated in the Particular Conditions, the Commencement Date shall be within 42 days after the Contractor receives the LoA [Letter of Acceptance]...” The FIDIC Guide defines the “Commencement Date” is the date on which the Time for Completion [Contract Duration] commences.
Ramadhan, in view of the above it’s imperative the contract to be crystal clear on the commencement date/contract effective date in order to avoid ambiguities in the contract interpretation especially in case of delays. My experience is that contract commencement date is one of the contentious issues in delays claims particularly when terms are not clear on the commencement date.
In delays analysis [valuation of claims relating to delays] particularly on Contract Commencement Date, one will be interested to identify whether the delay is compensable - excusable delays [responsibility borne by the client – caused by the client ], non-compensable –excusable delays [is acts of God or a third party- caused by factors beyond both parities] and or non-excusable delay [responsibility borne by the contractor – caused by the contractors] in order to establish the guilty party.
Normally the contract should have a date stated as the Contract Date/Contract Effective Date or Contract Commencement Date. This date is not necessarily the date when the contract was signed or letter of acceptance was issued but rather the date from which all the contractual rights and obligations begin and from which point any term of time, usually commences. In other words, date when the parties to the contract starting to perform their obligations in the contract.
I will try to breakdown your concerns based on the PPA 2004 and its Regulations and Form of Contract issued by PPRA as well as practice in other Form of Contracts.
According to S55(7)/PPA2005 “the procurement contract shall enter into force when a written acceptance of a tender has been communicated to the successful supplier, contractor or consultant”. To me this doesn’t mark the Contract Commencement Date but rather establishing the contract between the parties [offer + acceptance = contract]. For the parties to the contract to start performing their obligations there are conditions precedent must be meet in order to fix the Contract Commencement Date. One of these conditions is the submission of the Performance Security and signing of the contract within 30 days after receipt of the Letter of Acceptance.
Site Possession Date is the date when the contractor is given full access to the site by the client for temporary and permanent works. Logically, this cannot happen before the conditions precedent mentioned above are fulfilled by the contractor as ITB Clause [Performance Security] warrant the client to cancel the award and take any remedy under contract and resort to awarding the contract to the next ranked tenderer in case successful tenderer failure to comply with conditions precedent.
According to Clause 18 [Commencement and Completion] of the Form of Contract [Smaller Works Contracts] issued by PPRA, “The contractor may commence execution of the on the Start Date [stated in SCC] and shall carry out the works in accordance with programme submitted by the contractor, as updated with the approval of the Project Manager, and complete them by the Intended Completion Date [stated in SCC]”. The same Form of Contract Clause 24 [Possession of the Site] states that “The employer shall give possession of the site to the contract. If the possession of a part is not given by the date stated in the SCC, the employer will be deemed to have delayed the start of relevant activities, and this will be a Compensation Event”.
FIDIC – Form of Contract
In the 1999 FIDIC Conditions of Contract, Sub-Clause 8.1 [Commencement Date] states that "The Engineer shall give the contractor not less than 7 days’ notice of the Commencement Date. Unless otherwise stated in the Particular Conditions, the Commencement Date shall be within 42 days after the Contractor receives the LoA [Letter of Acceptance]...” The FIDIC Guide defines the “Commencement Date” is the date on which the Time for Completion [Contract Duration] commences.
Ramadhan, in view of the above it’s imperative the contract to be crystal clear on the commencement date/contract effective date in order to avoid ambiguities in the contract interpretation especially in case of delays. My experience is that contract commencement date is one of the contentious issues in delays claims particularly when terms are not clear on the commencement date.
In delays analysis [valuation of claims relating to delays] particularly on Contract Commencement Date, one will be interested to identify whether the delay is compensable - excusable delays [responsibility borne by the client – caused by the client ], non-compensable –excusable delays [is acts of God or a third party- caused by factors beyond both parities] and or non-excusable delay [responsibility borne by the contractor – caused by the contractors] in order to establish the guilty party.
RJM- Posts : 260
Join date : 2009-07-30
Age : 73
Location : What is written without effort is in general read without pleasure
commecement contract.
Hellow! Forumnist
My question today is when the contract commerncing, is normally commence after awarding and acceptance, or normally commernce after signing two parties, because it noramlly contractor may posses site, but when executing the work later come to claim that commercement of the work have to be counted from the date when legal contract have been signed.
I submit.
ramadhan- Posts : 3
Join date : 2010-08-06
Similar topics
» Effectiveness of the Contract
» ZERO CONTRACT part II
» Establishing contract between PE's
» When Does a Contract Starts
» Framework Contract
» ZERO CONTRACT part II
» Establishing contract between PE's
» When Does a Contract Starts
» Framework Contract
Page 1 of 1
Permissions in this forum:
You cannot reply to topics in this forum
|
|
Wed Dec 18, 2019 9:13 pm by yohanaamon@yahoo.com
» Is non-submission of invalid CRB receipt voucher a major deviation?
Tue Dec 17, 2019 1:00 am by RJM
» MAKANDARASI KUWEKWA NDANI KWA KUTOKAMILISHA MIRADI NDANI YA MUDA
Tue Dec 17, 2019 12:46 am by RJM
» How Supplier can register in e-Procurement system (TANePS)
Thu Dec 12, 2019 5:48 am by pms
» Kukosekana risiti ya ununuzi wa tenda
Sat Apr 27, 2019 6:05 pm by ALLY MUNIR
» IS IT TIME TO THINK OF DEACTIVATING TENDER BOARDS AND INTRODUCE A MECHANISM OF PROCUREMENT PROFESSIONAL OPINION?
Thu Apr 11, 2019 3:40 pm by pms
» e-Procurement System is now operational
Thu Apr 11, 2019 3:14 pm by Admin
» TENDA ZINAPOKOSA WAOMBAJI
Thu Jan 10, 2019 10:42 pm by thanksme
» Attendance of District Treasurer in Council Tender Board meetings
Mon Mar 19, 2018 8:57 pm by GWK