SUBMISSION OF BIDS AND COPIES
3 posters
Tanzania Public Procurement Forum :: PUBLIC PROCUREMENT ACT AND REGULATIONS :: Procurement of Goods, Works and Non Consultancy Services
Page 1 of 1
Re: SUBMISSION OF BIDS AND COPIES
Chimola + RJM,
Chimola posted a very relevant question- why do we need an original and copies?
To my knowledge is that you need copies for evaluation purposes. The copies are the ones that are handed over to the evaluation committee - of course after checking that they true copies of the original. The original is supposed to be kept in a safe place for references in case there are problems with the copies.
SORRY- THIS IS THE SAME RESPONSE THAT WAS GIVEN BY RJM
Chimola posted a very relevant question- why do we need an original and copies?
To my knowledge is that you need copies for evaluation purposes. The copies are the ones that are handed over to the evaluation committee - of course after checking that they true copies of the original. The original is supposed to be kept in a safe place for references in case there are problems with the copies.
SORRY- THIS IS THE SAME RESPONSE THAT WAS GIVEN BY RJM
RSM- Posts : 150
Join date : 2009-08-11
Re: SUBMISSION OF BIDS AND COPIES
I just received an e-mail through the forum – thanks to the technology, requesting me to clarify on my second argument “Action to be taken if only original submitted – opening the bids as usual. Never never turn bids opening meeting to evaluation committee”.
If original copy was submitted, then no doubt that bids opening will continue as planned OR even if copies submitted the bids opening will continue [I guess this might escalate more discussions – Are the copies not bid?].
Chimola, according to S66(3)/PPA2004 all bids submitted before the deadline time and date for submission shall be opened in public ……….. . To me this implies that anything submitted before such date and time and complies particularly to the submission instructions giving in the bidding documents, it is construed as a bid – without bother whether it is original or copies. I don’t think bids opening committee has mandate either to question why original only was submitted or not to open whatever was submitted. The responsibility of the bids opening committee is to open bids not to evaluate. That’s why I said that “Never never turn bids opening meeting into evaluation exercise”. The principles procedures for bids opening are normal adequately covered in the bidding documents which are derived from the regulations.
It should be kept in mind that, it is the Evaluation Committees which have mandate to determine whether submitting only original or copies is deviation or not according to the terms and condition contained in the bidding documents also with the help of tests provided in R90(/97/2005 to ascertain whether the deviation is “minor” or “major” in order to conclude on the responsiveness of the bid in question. However, here due care should be exercised!
If original copy was submitted, then no doubt that bids opening will continue as planned OR even if copies submitted the bids opening will continue [I guess this might escalate more discussions – Are the copies not bid?].
Chimola, according to S66(3)/PPA2004 all bids submitted before the deadline time and date for submission shall be opened in public ……….. . To me this implies that anything submitted before such date and time and complies particularly to the submission instructions giving in the bidding documents, it is construed as a bid – without bother whether it is original or copies. I don’t think bids opening committee has mandate either to question why original only was submitted or not to open whatever was submitted. The responsibility of the bids opening committee is to open bids not to evaluate. That’s why I said that “Never never turn bids opening meeting into evaluation exercise”. The principles procedures for bids opening are normal adequately covered in the bidding documents which are derived from the regulations.
It should be kept in mind that, it is the Evaluation Committees which have mandate to determine whether submitting only original or copies is deviation or not according to the terms and condition contained in the bidding documents also with the help of tests provided in R90(/97/2005 to ascertain whether the deviation is “minor” or “major” in order to conclude on the responsiveness of the bid in question. However, here due care should be exercised!
RJM- Posts : 260
Join date : 2009-07-30
Age : 73
Location : What is written without effort is in general read without pleasure
Re: SUBMISSION OF BIDS AND COPIES
Chimola,
You are most welcome to the KM Database.
1. Simply, copies are required to easy evaluation process - evaluation committee to work on copies and original kept in the safe custody and in discrepancy your revert to the original document.
2. Action to be taken if only original submitted - opening the bids as usual. Never never turn bids opening meeting to evaluation committee.
Chimola, I hope there is more you want to tell us- I argue to go ahead!
You are most welcome to the KM Database.
1. Simply, copies are required to easy evaluation process - evaluation committee to work on copies and original kept in the safe custody and in discrepancy your revert to the original document.
2. Action to be taken if only original submitted - opening the bids as usual. Never never turn bids opening meeting to evaluation committee.
Chimola, I hope there is more you want to tell us- I argue to go ahead!
RJM- Posts : 260
Join date : 2009-07-30
Age : 73
Location : What is written without effort is in general read without pleasure
SUBMISSION OF BIDS AND COPIES
I would like to know few things about bid and number of copies to be returned.
i. Why copies needed.
ii. If in the Bid Data Sheet it was indicated that:-The number of copies to be completed and returned with the bid is one original and two copies. During opening One Bidder submit only Original what action to be taken.
i. Why copies needed.
ii. If in the Bid Data Sheet it was indicated that:-The number of copies to be completed and returned with the bid is one original and two copies. During opening One Bidder submit only Original what action to be taken.
Chimola- Posts : 4
Join date : 2009-08-11
Location : Dodoma
Similar topics
» Submission of Late Bids
» HANDLING OF LATE BIDS/PROPOSALS DURING BIDS/PROPOSALS OPENING CEREMONY
» Discrepancy between copies and orignal of the submitted bidding documents
» DIRREFENCE IN TENDER REFERNCE NUMBERS
» Is non-submission of invalid CRB receipt voucher a major deviation?
» HANDLING OF LATE BIDS/PROPOSALS DURING BIDS/PROPOSALS OPENING CEREMONY
» Discrepancy between copies and orignal of the submitted bidding documents
» DIRREFENCE IN TENDER REFERNCE NUMBERS
» Is non-submission of invalid CRB receipt voucher a major deviation?
Tanzania Public Procurement Forum :: PUBLIC PROCUREMENT ACT AND REGULATIONS :: Procurement of Goods, Works and Non Consultancy Services
Page 1 of 1
Permissions in this forum:
You cannot reply to topics in this forum
|
|
Wed Dec 18, 2019 9:13 pm by yohanaamon@yahoo.com
» Is non-submission of invalid CRB receipt voucher a major deviation?
Tue Dec 17, 2019 1:00 am by RJM
» MAKANDARASI KUWEKWA NDANI KWA KUTOKAMILISHA MIRADI NDANI YA MUDA
Tue Dec 17, 2019 12:46 am by RJM
» How Supplier can register in e-Procurement system (TANePS)
Thu Dec 12, 2019 5:48 am by pms
» Kukosekana risiti ya ununuzi wa tenda
Sat Apr 27, 2019 6:05 pm by ALLY MUNIR
» IS IT TIME TO THINK OF DEACTIVATING TENDER BOARDS AND INTRODUCE A MECHANISM OF PROCUREMENT PROFESSIONAL OPINION?
Thu Apr 11, 2019 3:40 pm by pms
» e-Procurement System is now operational
Thu Apr 11, 2019 3:14 pm by Admin
» TENDA ZINAPOKOSA WAOMBAJI
Thu Jan 10, 2019 10:42 pm by thanksme
» Attendance of District Treasurer in Council Tender Board meetings
Mon Mar 19, 2018 8:57 pm by GWK