LIQUIDATED AND ASCERTAIN DAMAGES EmptyWed Dec 18, 2019 9:13 pm by yohanaamon@yahoo.com

» Is non-submission of invalid CRB receipt voucher a major deviation?
LIQUIDATED AND ASCERTAIN DAMAGES EmptyTue Dec 17, 2019 1:00 am by RJM

» MAKANDARASI KUWEKWA NDANI KWA KUTOKAMILISHA MIRADI NDANI YA MUDA
LIQUIDATED AND ASCERTAIN DAMAGES EmptyTue Dec 17, 2019 12:46 am by RJM

» How Supplier can register in e-Procurement system (TANePS)
LIQUIDATED AND ASCERTAIN DAMAGES EmptyThu Dec 12, 2019 5:48 am by pms

» Kukosekana risiti ya ununuzi wa tenda
LIQUIDATED AND ASCERTAIN DAMAGES EmptySat Apr 27, 2019 6:05 pm by ALLY MUNIR

» IS IT TIME TO THINK OF DEACTIVATING TENDER BOARDS AND INTRODUCE A MECHANISM OF PROCUREMENT PROFESSIONAL OPINION?
LIQUIDATED AND ASCERTAIN DAMAGES EmptyThu Apr 11, 2019 3:40 pm by pms

» e-Procurement System is now operational
LIQUIDATED AND ASCERTAIN DAMAGES EmptyThu Apr 11, 2019 3:14 pm by Admin

» TENDA ZINAPOKOSA WAOMBAJI
LIQUIDATED AND ASCERTAIN DAMAGES EmptyThu Jan 10, 2019 10:42 pm by thanksme

» Attendance of District Treasurer in Council Tender Board meetings
LIQUIDATED AND ASCERTAIN DAMAGES EmptyMon Mar 19, 2018 8:57 pm by GWK

April 2024
MonTueWedThuFriSatSun
1234567
891011121314
15161718192021
22232425262728
2930     

Calendar Calendar

Statistics
We have 1676 registered users
The newest registered user is esagile

Our users have posted a total of 1240 messages in 351 subjects
Who is online?
In total there are 2 users online :: 0 Registered, 0 Hidden and 2 Guests :: 2 Bots

None

[ View the whole list ]


Most users ever online was 225 on Sun Oct 03, 2021 4:24 pm

LIQUIDATED AND ASCERTAIN DAMAGES

4 posters

Go down

LIQUIDATED AND ASCERTAIN DAMAGES Empty Re: LIQUIDATED AND ASCERTAIN DAMAGES

Post  GEVE Thu Jun 24, 2010 4:21 am

RJM, this is may be interesting as well, when contractor pleads that LADs are "penalty" in the contract it mean that he claims that a foul has been committed in the contract by the Client/Employer, therefore he requests for the Court to intervene so a particulary LAds clause sholud be declared invalid and unenforceable.
.

Just to clarify few issues, if you go to the Standard Bidding Documents by PPRA which are in use by PEs, among listed documents forming part of the contractors/suppliers bid is General Conditions of Contract (GCC) and Special Consirtions of Contracts (SCC).

As far as LADs are concerned, Clause 52 of the GCC provides:

52.1 The Contractor shall pay liquidated damages to the Employer at the rate per day stated in the Special Conditions of Contract for each day that the Completion Date is later than the Intended Completion Date. The total amount of liquidated damages shall not exceed the amount defined in the Special Conditions of Contract. The Employer may deduct liquidated damages from payments due to the Contractor. Payment of liquidated damages shall not affect the Contractor’s liabilities.

52.2 If the Intended Completion Date is extended after liquidated damages have been paid, the Project Manager shall correct any overpayment of liquidated damages by the Contractor by adjusting the next payment certificate. The Contractor shall be paid interest on the overpayment, calculated from the date of payment to the date of repayment, at the rates specified in Sub-Clause 46.1.

52.3 If the Contractor has not corrected a defects within the time specified in the Employer’s notice, the Employer will assess the cost of having the defect corrected, the Contractor will pay this amount, and a penalty for lack of performance calculated as described in Clause 38.


If you go to the corresponding clauses of the SCC (clause 23), you may see that the Employer is left to insert the calculated LADs based on ceiling provided for in the Regulations ie 0.1 and 0.15 percent of contract price per day and the the maximum of which should be equivalent to the amount of the performance security.

Performance Security:

Clause 55.1 of the GCC provides:

" 1. The Performance Security shall be provided to the Employer no later than the date specified in the Letter of Acceptance and shall be issued in an amount and form and by a bank or surety acceptable to the Employer, and denominated in the types and proportions of the currencies in which the Contract Price is payable.

2. The Performance Security shall be valid until a date 28 days from the date of issue of the Certificate of Completion in the case of a Bank Guarantee, and until one year from the date of issue of the Completion Certificate in the case of a Performance Bond.


Performance Security is required to be a minimum amount equivalent to 10 to 15 percent of the contract price (Clause 26 of SCC read with Reg .

Regulation 88(7) od the GN NO. 97/2005 provides that the tender security of the successful tenderer shall be discharged when the tenderer has signed the contract and furnished the required performance security to the satisfaction of the procuring entity.

Persuant to Regulation 123(5), performace Security operates as a remedy to protect the PE in the event that a service provider or contractor fails to provide services at the required standard, to remedy faults or to complete the works to the satisfaction of the procuring entity, that procuring entity may either. In that situation a PE can eiher, withhold payment of any moneys retained, call any performance security if such has been furnished by the service provider or contractor.


Calculation of the Liquidated damages


In its context, LADs are based on "genuine pre-estimated loss" recorded in the contract to be paid by the contractor/supplier or service provider for each day, week or other period which the completion is delayed. The amount may be held by the Court to be penalty if they do not represent or reflect the likely financial loss or costs incurred by the Employer/Client. In a situation, the employer can end up recovering the actual loss suffered for the breach of contract under the common law.
The law requires that LADs to be inserted in the contracts, for a particular item of work should be related to the expected loss of profit of such work for each day that the Employer is deprived of it possesion/ use due to the delay by the contractor. However, in calculating the damages, the Court always do not consider accurateness of the figures as intended profit in the pre- assesment. It can be indirect loss eg loss of amenity for use/enjoyment which may be differently from commercial profit based on actual income.

The court also may refuse to enforce the clause for LADs and held it to be punitive if the fixed rate of LADs is higher than the actual value of construction the work itself. eg LADS of Tshs. 1, 000, 000 for a delay of completing a water reservoir whose construction value is Tshs. 100,000, can not in any way be held as reasonable loss, therefore is a penalty.

On the other scenerio, the Employer/ Client will be deprived to claim for the LADS of the full value of contracted works if at all the contract involves sectional completion and the Employer has requested the contractor/service provider for a partial possesion of a sectional completed work.
(eg see Clause 2.2 of the standard GCC which provides: If sectional completion is specified in the Special Conditions of Contract, references in the Conditions of Contract to the Works, the Completion Date, and the Intended Completion Date apply to any Section of the Works (other than references to the Completion Date and Intended Completion Date for the whole of the Works).

Courts' interpretation of LADs Clause


In the well known case of Dunlop Ltd v New Garage Co Ltd [l9l5] AC 79 Lord Dunedin set out the test for determining whether a sum was liquidated damages or a penalty. In the case it was considered that the court must find out whether the payment stipulated is in truth a penalty or liquidated damages, irrespective of the words used by the parties.

The essence of a penalty is that it is stipulated in terrorem of the offending party whereas the essence of liquidated damages is a genuine pre-estimate of damage. The Courts consideration must take into account the circumstances which existed at the time the contract was made and not when it was breached.

In that case it was noted that a clause is penal if it provides for “a payment of money stipulated as in terrorem of the offending party”, (i.e. a payment of a sum of money intended to frighten or intimidate the offending party). A clause that is found to be penal (i.e. a penalty clause) is generally invalid, and it is an unusual feature of the law of contract that the court will strike down penalty clauses, whilst (usually) permitting other clauses which have been freely agreed between the parties even if those clause are unduly harsh.

In another case of case of Imperial Tobacco Co. v Parslay [l936] 2 All ER 5l5, it was observed that the unequal financial posi tion of the parties is irrelevant as is any question of disproportion between the amount of the contract sum and the agreed sum payable on breach. There is a presumption that it is a penalty when a single lump sum is payable by way of compensation on the occurrence of one or more or all of several events some of which may occasion serious and others but trifling damage (Laird Brothers v City of Dublin Steam Packet Company (l990) 34 ILTR 9) It is no obstacle to the sum stipulated being a genuine pre-estimate of damage that the consequences of breach are such as to make precise pre-estimation almost an impossibility.

in the case of Campbell Discount Co Ltd v Bridge [1962] AC 600, the House of Lords struck down as a penalty a clause in a hire purchase agreement requiring the hirer to pay compensation for premature termination. The objectionable feature of this clause was that it provided a sliding scale which operated in the wrong direction. The less the depreciation of the vehicle, the greater was the compensation payable.


In the other case of Alfred McAlpine Capital Projects Limited v Tilebox Limited, was that on 27 April 2001, Tilebox and McAlpine entered into a written building contract. Clause 24 of the contract conditions provided that McAlpine should pay liquidated and ascertained damages for delay at the rate at the rate of £45,000 per week or part thereof. The Contract Completion Date was 14 August 2002, but building works were not completed by that date, and the works were not expected to be complete until June 2005 (i.e. some 2½ years late).

Against this background, McAlpine became concerned about its potential liability (of something approaching £6 Million) to liquidated and ascertained damages under clause 24 of the contract conditions. McAlpine took legal advice and, having done so, formed the view that the rate of liquidated and ascertained damages specified in the building contract was excessive, and was a penalty clause and was therefore invalid. Tilebox denied that clause 24.2 was a penalty clause.

The parties referred this matter to court, and in the court and the Court, considered the authorities and made the following general observation:-

(i) That a pre-estimate of damages does not have to be right in order to be reasonable. There must be a substantial discrepancy between the level of damages stipulated in the contract and the level of damages which is likely to be suffered before it can be said that the agreed pre-estimate is unreasonable.
(ii) Although many authorities use or echo the phrase "genuine pre-estimate", the test does not turn upon the genuineness or honesty of the party or parties who made the pre-estimate. The test is primarily an objective one, even though the court has some regard to the thought processes of the parties at the time of contracting.

(iii) Because the rule about penalties is an anomaly within the law of contract, the courts are predisposed, where possible, to uphold contractual terms which fix the level of damages for breach. This predisposition is even stronger in the case of commercial contracts freely entered into between parties of comparable bargaining power.

Based upon the above, the Court formed the view that the LADs in question was not a penalty clause, and therefore would be enforced.

Conclusion
For the LADs clause to be regarded as penalty in the contrary will depaend upon a case to case basis. However, the Courts are always smart not to interfere with the freedom of the parties to enter into contract. Therefore, if there the contractor/service provided had agreed on the clauses by signing the same, the court may uphold contractual terms in the same ways as agreed between the parties.

In the circumstances, the basis of challenging the clause can be considered during negotiation of the agreement before signing.

GEVE

Posts : 10
Join date : 2010-06-16

Back to top Go down

LIQUIDATED AND ASCERTAIN DAMAGES Empty Re: LIQUIDATED AND ASCERTAIN DAMAGES

Post  RJM Wed Jun 23, 2010 6:00 pm

GEVE, I just this pick this in your submission for further discussion and understanding.

The Contractors can have a valid defence against the Employers' right to LADs as follows:
(i) The agreed sum is a penalty (The court must find out whether the payment stipulated is in truth a penalty or liquidated damages, irrespective of the words used by the parties. LADs which are not genuine pre-estimate of damage can not apply)
R119/97/2005 relating to liquated dames says [reproduced below]

119-(1) Liquidated damages rates per day to be imposed on the supplier, service provider or contractor for undelivered materials or goods, undelivered or delayed service, or delayed works shall be as follows:
(a) in cases of procurement of goods or materials, the liquidated damages shall be imposed at 0.10 up to 0.20 per cent of the contract value of undelivered materials/goods, up to a sum equivalent to the amount of the performance guarantee.

(b) in cases of procurement of works, the liquidated damages shall be imposed at 0.10 up to 0.15 per cent of the contract value up to a sum equivalent to the amount of the performance guarantee.

(2) The liquidated damages rates shall be specified in the request for proposals or the tender documents and also in the contract and the maximum amount of the liquidated damages shall be equal to the amount of the performance bond or guarantee established in the contract.

GEVE, I agree with you that court may challenge the LADs to determine whether it is penalty or pre-estimate damages employer likely to suffer in case of delay. As we all know the ranges of LADs provided above [R119/97/2005] are normal incorporated in the standard bidding and contract documents whereby PEs select LADs to govern the contract within the range without real care whether it presents pre-estimate damages in case of delay. Now, I wonder if in some situations, this can be challenged by the contractor, service providers or suppliers that LADs in the bid and contract documents are penalty not are not based on pre-estimated damages. It is obvious that PEs defense will be the ranges have been provided in the in the regulations governing the procurement in the country and we are obliged to adhere.

What is your view on this?
RJM
RJM

Posts : 260
Join date : 2009-07-30
Age : 73
Location : What is written without effort is in general read without pleasure

Back to top Go down

LIQUIDATED AND ASCERTAIN DAMAGES Empty Re: LIQUIDATED AND ASCERTAIN DAMAGES

Post  GEVE Fri Jun 18, 2010 6:05 am

Thanks RSM

I do appreciate to find this forum for exchanging various ideas and views on procurement and contracts management.

Just in case, for the interested members in the construction industry, there are a lot useful materials online relating to the isssues in our discussion.

You may wish to visist the following links.

http://www.contractjournal.com/Home/
http://www.scl.org.uk/
http://www.constructionarbitrators.org/publications.htm
http://www.bre.co.uk/
http://www.construction-on-line.co.uk/

GEVE

Posts : 10
Join date : 2010-06-16

Back to top Go down

LIQUIDATED AND ASCERTAIN DAMAGES Empty Re: LIQUIDATED AND ASCERTAIN DAMAGES

Post  RSM Thu Jun 17, 2010 5:16 pm

Geve,

Welcome to the forum and let me start by quoting you

I read this confusion on the issue of retention money and Liquidated damages.

We are happy that you have joined the forum. There is no confusion, we want people to discuss and air their views and the wish is to have people like you coming in and discussing with references and facts. This way we can make the forum a resource for procurement experts and others interested in the subject matter.

We look forward for more of your contibutions. The two that I have read so far, this one and that on PPAA rulings tells us that we have a serious entrant in the forum. What do other forum members think?

RSM

Posts : 150
Join date : 2009-08-11

Back to top Go down

LIQUIDATED AND ASCERTAIN DAMAGES Empty RETENTION vs LIQUIDATED DAMAGES

Post  GEVE Wed Jun 16, 2010 5:06 pm

I read this confusion on the issue of retention money and Liquidated damages. Just from some of us how may be not clear on the two, it is not for the purposes of law to provide for the right of the parties in the contract (any of). But it is for the parties themselves to agree o what they want the law to protect them in case of any dispute.

Retention money/ Fund is the amount of money which the employer/client can insert and agree with contractor in the construction of contract to be deducted from payment due to the contract for the purposes of protecting the employer in case that the works are not well completed inaccoradnce with the contract. Therefore, retention can be used to rectify the defect without prejudice to the other remedies which the employer may opt if things goes wrong in the oroject contrary to the expection. Retention money as the word sounds, can be deducted from IPCs and retained up to the date of issuance of Practical/substantial completion certificate whereby the half moiety has to be refunded to the contractor and the rest to be refunded upon issuance of completion/final certificate. Retention is only the employers maoney when the defects on the works occurs and the contractors fails to remedy the same hence to make the employer use the money. Otherwise, they will remain to be Contractor's monies.

LADs.

Most of the Standard Construction contracts provide for express terms and conditions as obligation of both the Employer and the Contractor therein. In and case such terms are not expresses provided, they will be deemed to be implied applicable in the said contracts under the common law in order to protect the rights and ensure the obligations of each party to the contracts is well performed. For example among the obligations which the contractor has in the construction contract included:
(i) an obligation to complete work by certain completion date or specified period;
(ii) an obligation to progress the work regularly and diligently; and


While on the other hand the employer has an obligation generally to facilitate the work of the contractor including:
(i) to appoint the contracts administration team as earlier as possible
(ii) to paid the contractor in accordance with the agreed contract price or such sum as due to adjustment of contract price,
(iii) to provide required information or materials to the contractor to enable him execute the work properly; and
(iv) not to interfere with the progress of work by the contract.

With an obligation to execute and complete the work according to the agreed completion date, the Contract may be liable to the Employer for the breach of the contract if fails comply with the contract period. Breach of contract by failure to comply with completion date, may entitle the contractor to pay both liquidated and unliquidated damages.

Liquidated damages are intended to be a genuine pre-estimate of the Employer’s losses in the event
of delay. As opposed to the general damaged for which the employer can be entiled to prove actual loss, LADs can be claimed even without any need to proof any loss .

Where the contract provides for LADs in the sum of X Tzs to be payable for each week of delay, and the contractor fails to complete on time, the Employer is prima facie liable to claim for liquidated damages without further enquiry. In fact an Employer is entitled to claim liquidated damages even if he has suffered no actual loss (Clydebank Engineering and Shipbuilding Company v Castaneda [l905] AC 6)

For the employer to have a right to claim for LADs, the following conditions must apply:
(i) there must be an express provision in the contract giving the employer a right to LADs in case the completion date of the project is set behind the intended/ agreed date for compleate;
(ii) there completion date must be delayed by the contractor's risk events/faults;
(iii) There should be a mechanism to ascertain damages payable set in prior and be respond to the relevant portion of work alleged to have been delayed (certanity as to the amount and dates to be calculated and paid).

It appears that if the contract provides for a " TzsNIL" percentage of LADs, then the Court will end up decsiding to award the employer a "NIL" as the one agreed by the parties and not otherwise.
For example in the case of Temloc Limited v Errill Properties Limited (l987) 39 BLR 30 the parties to a JCT 80 Standard Form of Contract, stated the liquidated damages recoverable under Clause 24.2 to be "£Nil". The Employer sought to argue that there was no liquidated damages clause and that they were entitled to claim general damages. The Court of Appeal held that the effect of "£Nil" was that a proper construction of the contract was that it had been agreed that there should be no damages for delayed completion.

It should be noted that the employer may not have a right to claim for the LADs where completion has been interfered by factors which are not within the control of the Contractor (such can be considered as as Employers acts or omissions or events which are not in the control of either of the parties such as increment averse weather etc, construction contracts allow for the contract administration or Architect to extended completion date beyond).

The LADs provisons can sometimes go with extension of time provisions in the contract to allow the Employer through Archutect or Engineer, to extend time inevent of delay of completion for which the contractor is responsible. Otherwise, if the contract contains no EOT provision or is unclear on powers of the Employer to extend time, then at common law, time is said to be set as large and the employer can not claim for LADs. In such situation, the Employer can only have a right to claim for general damages which can be proved.

Extension of Time:

EOT is one of the admistrative powers of the Architect or Engineer under the Construction contract to allow for more time to the contractor so as he can complete the works at further agreed date beyong the initial intended completin date. In one case of Rapid Building Group Limited v Ealing Family Housing Association (1984) 29 BLR 5, it was considered that the purposes of EOT provision in the contract are:
(i) to relieve the contractor of liability for paying damages (LADS) to the Employer for any period prior to EOT; and
(ii) to enable the employer to maintain a proper date from which LADs can be calculate in the event the employer has presvented the contractor from completing the works.

In the other case of Peak Construction (Liverpool) Ltd vs McKinney Foundation Ltd (1970) 1 BLR, the court was of the views that the LAD and EOT clauses in printed forms of contract must be construed strictly contra proferentem. In this case, it was considered that if the contractor fails to complete the works on time by the wholly or party fault due the employer, then the EOT clause should provide, expressly or by necessary inference, for an extension on account of such a fault or breach on the part of the employer, otherwise time would be “at large” and the employer will loss right to LADs.

Therefore, clear provisions in the contract are required for dealing with the Retention monies, LADs and even EOT.

Contractors defence

The Contractors can have a valid defence against the Employers' right to LADs as follows:
(i) The agreed sum is a penalty (The court must find out whether the payment stipulated is in truth a penalty or liquidated damages, irrespective of the words used by the parties. LADs which are not genuine pre-estimate of damage can not apply)
(ii) The contractual provisions do not work (eg in a situation where a single sum is stipulated for liquidated damages but the works are to be completed in sections at different times or where the employer takes possession of part of the works before completion of the whole).
(iii) The delay was caused by the employer (eg ordering variations which will delay completion, failing to give possession of the site, delaying in giving necessary instructions.

GEVE

Posts : 10
Join date : 2010-06-16

Back to top Go down

LIQUIDATED AND ASCERTAIN DAMAGES Empty Re: LIQUIDATED AND ASCERTAIN DAMAGES

Post  RJM Thu Dec 10, 2009 4:30 pm

I am not aware of any legal impose limit on Liquidated Damages. However, I believe it makes sense to have a cap in the contract on the maximum LAD that will be imposed to the contractor in case of delay in the execution of the project. I am saying this especially because of difficulties that uncapped LAD may cause problem to the contractors in getting performance bonds. Guarantor/Insurer may refuse to bond the contractor or fix the bond premium at a high price, which will be passed on to the Client. Excessive risk may also cause inflated bid prices as bidders seek to cover themselves for a worst-case scenario.

RSM, I agreed with that extended delays will be construed that the contract has abandoned the works or plainly demonstrated the intention not to continue performance of his obligations under the contract and therefore give the client right to terminate the contract. This is the same when contractor stops work and stoppage is not shown in the work program and the stoppage has not been authorized by the Engineer. This will amount to breach of the contract.
RJM
RJM

Posts : 260
Join date : 2009-07-30
Age : 73
Location : What is written without effort is in general read without pleasure

Back to top Go down

LIQUIDATED AND ASCERTAIN DAMAGES Empty Re: LIQUIDATED AND ASCERTAIN DAMAGES

Post  RSM Thu Dec 03, 2009 11:43 am

RJM and Kurare,

I am afraid I came in late in this discussion, but I have one question that I need to put forward. Why do they put a limit in the amount of liquidated damages? A typical clause on delay damages ends like this ..... However, the total amount under this clause shall not exceed the maximum amount od delay damages (if any) stated in the SCC

My view is that at a certain point, extended delays shall be construed that the contractor has abondoned the works or has plainly demonstrated the intention not to continue performance of his obligations under the contract, and therefore give the Client the right to terminate the contract.

What do you say


Last edited by RSM on Mon Jun 07, 2010 10:57 pm; edited 1 time in total

RSM

Posts : 150
Join date : 2009-08-11

Back to top Go down

LIQUIDATED AND ASCERTAIN DAMAGES Empty Re: LIQUIDATED AND ASCERTAIN DAMAGES

Post  RJM Tue Dec 01, 2009 9:58 pm

This follow from the previous post.

Do we have a legal basis to withhold retention money as payment for delay penalties?

I am not sure if we real have any legislation permitting withhold retention money as payment for liquidated damages. I believe gurus will help us if there is any existing legislation.

In the course of researching on the issue I found that in UK they have what is called a Housing Grants, Construction and Regeneration Act 1996 which entitle an employer to withhold payments from a contractor as long as the employer complies with the provisions of the Act i.e. that it specifies the amounts to be withheld from any payment and the reasons for the withholding, within the time frame set out in the contract. Furthermore, this provision has been incorporated in their Standard Bidding Document. The right to set-off claims against the retention money is stipulated in JCT2005 [The Joint Contracts Tribunal – UK – Standard Building Contract] Clause 4.13.2 which states “notwithstanding the fiduciary interest of the employer in the retention as stated in Clause 4.18 the employer is entitled to exercise any right under this contract to withholding and/or deduction from the monies due to or become due the contractor …”. According to Clause 4.18 [Rules on Treatment of Retention] of JCT2005 retention money is the contractor’s money. Furthermore, Clause 4.18.3 states that “… if the contractor so requests, at the date of payment under each Interim Certificate place the retention in a separate banking account and certify to the Architect/Contract Administrator with a copy to the contractor that such amount has been so place..”. This caters for the event that employer goes bankruptcy/insolvent liquidation whereby the retention money will have to go to liquidator for distribution his creditors. Therefore, this imposes an implied obligation to set aside retention funds as a separate trust fund in favour of the contractor. Despite the fact that the terms and conditions of the contract impose obligation to set aside retention funds, in the preceding case of Henry Boot Building v Croydon Hotel, (1987) 36 BLR 41 (CA); the Court of Appeal dismissed the contractor appeal for injunction where Lord Justice Nourse said: “Although under Clause 30(4)(a) JCT the employer was under an obligation to appropriate and set aside amounts retained as a separate trust fund and that obligation could be enforced by the grant of a mandatory injunction, no such injunction could be granted at a time when the employer was entitled to deduct a greater amount of liquidated or ascertained damages because there was no subsisting obligation to appropriate and set aside” This implies that a court will not grant an injunction against employers who are making bone fide claims against retention monies.

Or should SBD for Smaller Works be interpreted as such that retention money is only destined for non compliance of the contractor regarding the quality of the work?

In UK, if the contract is silent you can offset the liquidated damages from the retention see case of GPT Realisations v Panatown (1992) 61 BLR 88 [in Administrative Receivership & Liquidation]. KURARE, since our SBDs are silent probably we go with this option. However, if you drain the pot for liquidated damages and defects occur, there will be little or no incentive for the contractor to make defects good/remedy the defects. Suppose you negotiate with the contractor as suggested by KURARE and contractor agreed with the proposal of deducting retention money as LAD, what is the security for the employer during Defect Liability Period/Maintenance Period?? This is very very trick as sometimes the Defect Liability Period for projects range from 6 - 36 months or could be more depends on uniqueness of the project. In case of defects do you think the contractor will come back?

KURARE, lesson learnt in this scenario is the important of the “Live’ Performance Bond/Guarantee in the execution of the project. If the contract is extended and performance security is not extended count yourself that there is no performance security exist. This means that you cannot write to the guarantor demanding to declare the contractor to be in default under the contract and draw the security as the security has already expired date. From KURARE post “The performance guarantee was extended two times but in the end the Contractor did not extend his performance guarantee, so I am afraid that we cannot draw this guarantee’. If yes, then you deduct liquidate damages until when is equal to amount of the performance bond or guarantee as per R119(2)/97/2005, then, determination as per GCC 62.2 (g) of the Small Work Contracts.


Last edited by RJM on Sat Dec 05, 2009 9:23 pm; edited 2 times in total
RJM
RJM

Posts : 260
Join date : 2009-07-30
Age : 73
Location : What is written without effort is in general read without pleasure

Back to top Go down

LIQUIDATED AND ASCERTAIN DAMAGES Empty Re: LIQUIDATED AND ASCERTAIN DAMAGES

Post  RJM Fri Nov 13, 2009 6:00 pm

KURARE, this is quite interesting debate. As part of preliminary analysis let us distinguish between RETENTION MONIES AND LIQUIDATED AND ASCERTAIN DAMAGES.

In contract management perspective, Retention Money (RM) is deducted from interim certificates at certain specified percentages up to an agreed maximum value specified in the Special Conditions of Contract. The money is safeguard to the client for the work done in case of any defects which will not be corrected by the contractors during contract execution and after issue of the substantially completion/practical completion certificate. Normally, in the process of administering contract, one half of the retention money is repaid to the contractor upon issuance of the practical completion certificate, and the other half upon the issue of Defect Liability Certificate.

In practical terms, prior issuing practical completion certificate, final inspection is done and snag list (defects works) is prepared by the consultant/supervisor which the contractor should rectified them during Defect Liability Period as specified in the contract. In case the contractor fail to rectify those defects during Defect Liability Period, then, the retained half of the retention money is used to rectify them. Therefore, the retention money is the contractor’s money and the client does not own it. I believe there is no express provision enabling the client to make use of the retention for any other purpose. [This deal with quality]

Liquidated and Ascertained Damages (LAD) are the rates per day/week/month imposed on the contractor for delayed works or are rates per day/week/month payable by the contractor to the client in the event of its failure to complete the contract by the time for completion. [This deal with performance]

If we examine the General Condition of Contract for Smaller Works Contract you are referring to, LDA and RT are dealt under different Clauses. Now can we withhold RT as LAD Question Question

More to follow!
RJM
RJM

Posts : 260
Join date : 2009-07-30
Age : 73
Location : What is written without effort is in general read without pleasure

Back to top Go down

LIQUIDATED AND ASCERTAIN DAMAGES Empty LIQUIDATED AND ASCERTAIN DAMAGES

Post  KURARE Thu Nov 05, 2009 2:03 pm

We are PE dealing with the contract for civil works using Standard Bidding Document for Smaller Works issued by PPRA wherein the time for completion was set at 12 months. The Contractor had a time overrun of 18 months and after deductions of unworkable day and delays caused by late approval of construction drawings the delay would still run to the maximum of 10% of delay damages foreseen in the contract. We propose to inform the contractor that not only he is to pay for these delay damages amounting to 10% of the Contract but also that we propose to withhold the payment of the retention money to pay for the delay damages. The performance guarantee was extended two times but in the end the Contractor did not extend his performance guarantee, so I am afraid that we cannot draw this guarantee.

My question: do we have a legal basis to withhold retention money as payment for delay penalties? I'm afraid that your answer will be no, but can we hope for entering in discussions with the contractor to come to some kind of agreement on this. Say negotiating into using this retention money as payment; or at least a part of it?
Or should SBD for Smaller Works be interpreted as such that retention money is only destined for non compliance of the contractor regarding the quality of the work?

KURARE

Posts : 2
Join date : 2009-10-24

Back to top Go down

LIQUIDATED AND ASCERTAIN DAMAGES Empty Re: LIQUIDATED AND ASCERTAIN DAMAGES